Unit Based Charge Calculation Guidelines - PM
Select Duration to:
-
Calculate the roll-up service charge based on the total component service duration.
-
The roll-up service fee is multiplied by the number of rendered component service units (the component service duration).
-
For example, a roll-up service has a fee of $125.
-
The roll-up service has a user-defined minutes per unit charge of 15 minutes per unit.
-
If the component services have a total duration of 60 minutes, the roll-up service fee is calculated using 4 units of service, for a total of $500.
Select Total Charge to:
-
Calculate the roll-up service charge based on the total component service charge.
Select Units to:
-
Multiply the roll-up service fee by the total component service units.